The Lagos State Commissioner for Transportation, Mr Oluwaseun Osiyemi, said this in a statement on Tuesday.

Osiyemi noted that the rehabilitation would cover the stretch from U-Turn Bus Stop to Sango Tollgate, affecting both inbound and outbound lanes.

“The rehabilitation work is scheduled to commence on Wednesday, Feb. 11, and end on Wednesday, March 11, spanning a period of four weeks,” he said.

Sponsored

He added that to minimise traffic disruption, the project would be executed in two phases.

“Phase one (Abeokuta-bound Traffic), scope of work: (U-Turn Bus Stop inward Sango Tollgate) and duration: Wednesday, Feb. 11 to Wednesday, March 4. (Three weeks)

“During this phase, traffic from Lagos/Abule-Egba inward Abeokuta/Sango Tollgate will be diverted to one half of the carriageway, approximately 20 metres away from the active work zone, and restored to full access after the work area.